VALID PRINCE2-AGILE-PRACTITIONER EXAM TOPICS & RELIABLE PRINCE2-AGILE-PRACTITIONER EXAM SYLLABUS

Valid PRINCE2-Agile-Practitioner Exam Topics & Reliable PRINCE2-Agile-Practitioner Exam Syllabus

Valid PRINCE2-Agile-Practitioner Exam Topics & Reliable PRINCE2-Agile-Practitioner Exam Syllabus

Blog Article

Tags: Valid PRINCE2-Agile-Practitioner Exam Topics, Reliable PRINCE2-Agile-Practitioner Exam Syllabus, Valid Braindumps PRINCE2-Agile-Practitioner Ppt, Detailed PRINCE2-Agile-Practitioner Study Dumps, PRINCE2-Agile-Practitioner Test Dumps.zip

I believe that after you use our PRINCE2-Agile-Practitioner study materials for a while, we will understand why we have a 99% pass rate. Our company has been pursuing the quality of our products. And our professional experts are the most specialized people in this career to help us pass the PRINCE2-Agile-Practitioner Exam. They have studied and done reseach on the design of our PRINCE2-Agile-Practitioner practice guide for over ten years. So every detail of our PRINCE2-Agile-Practitioner exam questions is perfect.

This is your right to have money-back guarantee, namely once but a full refund with the transcript. Some people worry about the complex refund of our PRINCE2-Agile-Practitioner exam practice, as a matter of fact, our refunding procedures are very simple. We will immediately refund if the buyer provide failure test proof just like failure score scan or screenshots. If you have any questions about our PRINCE2-Agile-Practitioner Preparation quiz, please contact us by online service or email, we will reply as soon as possible.

>> Valid PRINCE2-Agile-Practitioner Exam Topics <<

PRINCE2 Agile Practitioner Project Management Exam test for engine, PRINCE2-Agile-Practitioner VCE test engine

Our company is a professional certification exam materials provider. We have occupied in this field more than ten years, therefore we have rich experiences in providing valid exam dumps. PRINCE2-Agile-Practitioner training materials cover most of knowledge points for the exam, and you can improve your professional ability in the process of learning. PRINCE2-Agile-Practitioner Exam Materials are high-quality, and you can improve your efficiency while preparing for the exam. We offer you free demo for PRINCE2-Agile-Practitioner exam dumps, you can have a try before buying, so that you can have a deeper understanding of what you are going to buy.

PRINCE2 PRINCE2-Agile-Practitioner Exam Syllabus Topics:

TopicDetails
Topic 1
  • Skills and Processes: This section measures the capabilities of PRINCE2 Project Managers in utilizing best practice guidance for project delivery. It focuses on equipping professionals with the necessary skills to manage projects effectively in fast-paced environments.
Topic 2
  • Target Audience: This domain is designed for professionals working in project environments, particularly those responsible for integrating project management with product delivery. It outlines the certification's relevance for individuals looking to enhance their project management capabilities while maintaining governance and control.
Topic 3
  • PRINCE2 Agile® Practitioner Overview: This section of the exam measures the skills of PRINCE2 Project Managers and covers the integration of PRINCE2 and Agile methodologies. Candidates will learn how to effectively combine these approaches to create a comprehensive project management solution that balances control with flexibility.
Topic 4
  • Certification Validity: This section informs candidates about the certification's validity period, which is three years for PRINCE2 Agile Practitioner holders. The emphasis is on maintaining certification through either re-sitting the exam or engaging in AXELOS membership activities.
Topic 5
  • Project Management Solution: This domain is aimed at PRINCE2 Agile Practitioners and highlights the importance of a complete project management solution. It emphasizes the synergy between agile flexibility and the structured framework of PRINCE2.

PRINCE2 Agile Practitioner Project Management Exam Sample Questions (Q28-Q33):

NEW QUESTION # 28
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zerocost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
A local newspaper has reported the results of a survey. The survey indicated that local residents are concerned that costs from the event may be incurred by local tax payers.
Which action would have helped to avoid this situation?

  • A. Publishing regularly updated advertisements fisting the organizations that are sponsoring the event.
  • B. Sharing the delivery team's updated burn-charts with the local newspaper before the results of the survey were published.
  • C. Publishing updated costs of the event estimated using a points system.
  • D. Inviting a representative of the local press to participate and report upon a release review at the end of stage 4.

Answer: A

Explanation:
Regularly updating the public about the event's funding sources, particularly the sponsors, would have helped to alleviate concerns by clearly demonstrating that the event is being funded through external means rather than local taxpayer dollars. This transparency can build trust and reassure residents about the financial aspects of the event.


NEW QUESTION # 29
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

  • A. It applies the target poorly because the customer subject matter expert should represent the impacted stakeholders.
  • B. It applies the target poorly because the training acceptance criteria should be specified in the project product description.
  • C. It applies the target well because the training will be delivered in the most accurate way.
  • D. staff members are able to give advice on health and fitness.
    This is covered by four work packages:
    1. Training syllabus:
    * High-level design of the manual.
    * Content of each module.
    2. Course content for safety and professionalism:
    * Detailed design of two modules:
    * Health and Safety including basic first aid.
    * Customer relations to look after people attending the event.
    * Piloting the modules with a group of volunteers.
    3. Course content tor giving advice on health and fitness:
    * Detailed design of two modules:
    * Exercise fundamentals including how to warm up and cool down.
    * Healthy eating including what types of food are good for you.
    * Piloting the modules with a group of volunteers.
    4. Training delivery:
    * Production of the training manual;
    * Delivery of the training to the rest of the volunteers.
    The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
    Using the Project Scenario and Staff Training Additional information, answer the following question:
    The Staff Training Team had been working to the following assumption:
    'All volunteers will be trained in all training materials.'
    Quite late in the project, it has been identified that this assumption is incorrect. As a result, the team manager produced a chart of who needs to be trained in what modules. This was agreed with a customer representative and the team manager made the necessary amendments to the requirements in the backlog within the current timebox.
    What BEST explains why the team manager's approach complies with the 'embrace change' target?
  • E. the event is carried out safely and professionally;
  • F. It applies the target well because visualization is the most effective way to communicate change.

Answer: E

Explanation:
By recognizing the incorrect assumption and producing a chart to clarify who needs to be trained in which modules, the team manager is adapting to the new information and ensuring that the training is aligned with the actual needs. This responsiveness to change helps deliver training more effectively, reflecting the principle of embracing change to improve outcomes.


NEW QUESTION # 30
Which describes a characteristic of business as usual (BAU) work?

  • A. Lists of routine modifications, received regularly during the life of existing products. )
  • B. A delivery which is part of a larger programme of work.
  • C. A new team selected to address a specific problem or opportunity.
  • D. A collection of difficult tasks that are managed together.

Answer: A

Explanation:
Routine Operations: BAU encompasses the standard activities and processes that are necessary for the daily functioning of an organization. This includes tasks that are performed regularly and consistently to maintain services, products, and overall operations.
Regular Modifications: BAU work often involves minor updates or modifications to existing products or services. These modifications are typically routine in nature, aimed at improving efficiency, fixing issues, or adapting to changes in the environment without major disruption.
Maintenance and Support: BAU includes maintenance tasks such as monitoring systems, providing customer support, and ensuring compliance with regulations. These tasks ensure that existing products and services continue to function effectively.
Predictable and Structured: Unlike projects that may have a defined start and end date, BAU work is ongoing and tends to follow established procedures. This predictability helps organizations manage their resources effectively.
Focus on Stability: The goal of BAU work is to maintain stability within the organization. While it may involve some level of change (like routine modifications), the primary focus is on ensuring that existing operations run smoothly.


NEW QUESTION # 31
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through feespaid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
All public events supported by the LGA must be fully accessible to all visitors.
How should this requirement be recorded?

  • A. In the project product description for the tournament as a Customer Quality Expectation.
  • B. In a user story: 'As the LGA, I want to allow access to all visitors so that everyone can attend the tournament'.
  • C. Under the composition heading of project product description as a Must Have requirement.
  • D. On a burn chart as a feature to be delivered by the team within the current timebox.

Answer: A

Explanation:
Recording this requirement as a Customer Quality Expectation highlights its importance to the overall success of the event. It ensures that accessibility is recognized as a critical aspect that the project must meet to satisfy stakeholders and attendees, aligning with the principles of inclusivity in public events.


NEW QUESTION # 32
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager has agreed with the Website team manager delivering the Social Media work package that the team should try using the Kanban method along with their existing Scrum approach to improve delivery.
The team is now going to use a Kanban board as part of their information radiator.
Which explains the additional benefit of combining these two agile approaches during the 'managing product delivery' process?

  • A. Using Kanban limits the amount of scope change on the project and therefore increases velocity.
  • B. By using Kanban, collaborative working is enabled between members of the Website Team delivering the social media.
  • C. Using Kanban limits the amount of work being carried out by the team, with the aim of improving delivery during the sprint.
  • D. A Kanban board makes the status of the Social Media work package visible to the delivery team.

Answer: D

Explanation:
A Kanban board provides a visual representation of the workflow, making it easy for the team to see the status of tasks within the Social Media work package. This increased visibility helps the team manage their work more effectively, identify bottlenecks, and facilitate communication, enhancing overall productivity and coordination during the delivery process.


NEW QUESTION # 33
......

How can you quickly change your present situation and be competent for the new life, for jobs, in particular? The answer is using our PRINCE2-Agile-Practitioner practice materials. From my perspective, our free demo of PRINCE2-Agile-Practitioner exam questions is possessed with high quality which is second to none. This is no exaggeration at all. Just as what have been reflected in the statistics, the pass rate for those who have chosen our PRINCE2-Agile-Practitioner Exam Guide is as high as 99%, which in turn serves as the proof for the high quality of our PRINCE2-Agile-Practitioner practice torrent.

Reliable PRINCE2-Agile-Practitioner Exam Syllabus: https://www.actualtorrent.com/PRINCE2-Agile-Practitioner-questions-answers.html

Report this page